DEVELOPING
AND IMPLEMENTING THE SOLUTION
|
 |
INTRODUCTION |
|
6.1 |
Following
the identification and description of all costs, benefits and risks,
their valuation where feasible, and their testing through sensitivity
and scenario analysis, the best option should
be selected. Transparency is important at this stage, so that it
is clear on what basis decisions are taken. Judgement over and above
the component parts of the analysis is always called for in making
decisions, but the following guidelines should be applied.
|
6.2 |
Once
an option has been selected, it will need to be refined into a solution.
Consultation is important at this stage. Further consideration will
need to be given to the implementation of the proposal, including
the involvement of the private sector,
procurement options and processes, and the programme and project
management arrangements that may be required. |
SELECTING THE BEST OPTION
|
Decision
guidelines
|
6.3 |
If
a full cost benefit analysis has been undertaken, the best option
is likely to be the one with the highest risk adjusted net present
value. To the extent that all costs, benefits and risks have been
robustly valued, this guideline can be applied with more certainty.
In cost effectiveness analysis, the option with the lowest net present
cost should be the best, again assuming that the cost estimates
are as accurate and reliable as possible.
|
6.4 |
If
there is a budget ceiling, then the combination of proposals should
be chosen that maximises the value of benefits. The ratio of the
net present value to the expenditure falling within the constraint
can be a useful guide to developing the best combination of proposals.
|
| |
BOX
19: EXAMPLE – PROJECT CHOICE |
| |
Consider
the investment costs and expected net benefits of the following
proposals:
| |
£million
Initial investment |
Expected
net benefit (NPV) |
 |
| A |
10 |
4 |
| B |
6 |
3 |
| C |
4 |
3 |
 |
(a) |
If
the budget were constrained to £10 million,
proposals B and C would achieve the highest return,
rather than proposal A, even though proposal A has
the highest individual NPV. |
(b) |
If
it is possible that elements of proposals A, B and
C could be combined, within the constraint, to produce
a significantly higher return, this should be investigated.
|
|
|
6.5
|
Other decision criteria can be used to help select options where risk
is an important consideration. The ‘maximin-return’ option
is the most important to consider. It is the most risk averse option,
as it is the option that provides the least bad outcome if the worst
possible conditions prevail.
|
| |
back
to top
BOX
20: EXAMPLE – MAXIMIN RETURN
|
| |
Two government services are being
considered, which are mutually exclusive. Their NPVs under
different market conditions are shown below:
| |
Low
demand (£) |
Expected
value (£) |
High
demand (£) |
 |
| Service
A |
1,000,000 |
1,200,000 |
1,600,000 |
| Service
B |
100,000 |
1,250,000 |
2,000,000 |
 |
The
maximin criteria points to Service A, as it provides the
highest value in the worst market conditions.
|
|
6.6
|
In practice, other factors will also affect the selection of the
best option, in particular the cosideration
of unvalued costs and benefits. Weighting
and scoring techniques are useful
in comparing different options in terms of the same criteria. However,
as scores are not expressed in monetary terms, judgment is then
required to compare the results of weighting and scoring with the
cost benefit or cost effectiveness analysis. The two analyses should
complement each other, and may indicate that further analysis is
required before a decision can be reached. Annex 2 provides further
information on how weighting and scoring can be brought into the
decision making process. Fully involving stakeholders is very important
in making judgments between monetised and non-monetised effects.
|
6.7 |
There
is always a value imputed by decisions to proceed,
and this value should always be clearly identified and analysed.
|
| |
BOX
21: EXAMPLE – SELECTING THE BEST OPTION
|
| |
Two lead options are being considered, with net present
costs of £1 million and £3 million respectively,
after taking into account valued benefits. To select the
£3 million option, a decision maker would need to
judge that the unvalued benefits of the project must be
worth at least £2 million.
He
or she needs to judge whether this is reasonable. Several
considerations could help inform this judgment. Are there
any measures of the unvalued benefits that could be used
to derive unit values, which could help assess whether the
£2 million is in fact worthwhile? Have values for
this kind of benefit been estimated in other studies? Or
are there better opportunities elsewhere for using the £2
million? What do the stakeholders think? And importantly,
what do the stakeholders representing the opportunity of
using the £2 million elsewhere think?
|
|
6.8
|
The ‘pay back period’1
is sometimes put forward as a decision criterion. But payback ignores
the differences in values over time, and the wider impacts of proposals. These
drawbacks mean it should not generally be used as a decision criterion.
|
6.9 |
Similarly,
the ‘internal rate of return’2
(IRR) should be avoided as the decision
criterion. Whilst it is very similar to NPV as a criterion, there
are some circumstances in which it will provide different, and incorrect,
answers. For instance, IRR can rank projects that are mutually exclusive
differently from NPV.
|
|
back
to top
Affordability, funding,
and cashflows
|
6.10
|
The affordability of options should always be considered when developing
and selecting options. In addition to the analysis of economic costs
and benefits, appraisals usually need three major financial statements,
at least for the lead options:
|
| |
 |
A
budget statement. This should
be based on resource accounting and budgeting (RAB) principles,
and show the resource costs over the lifetime of the proposal.
For strategic initiatives, the budget will often comprise
the forecast RAB financial statements of a whole organisation
over a number of years. |
 |
A
cashflow statement. This should
show the additional cash that will be spent on the lead option
if it goes ahead. |
 |
A
funding statement.
This should show which internal departments, partners and
external organisations would provide the resources (and in
some cases cash) required. |
|
6.11
|
Contingency arrangements should also be developed to ensure there
is sufficient financial cover for risks and uncertainties.
|
| |
BOX
22: EXAMPLE – DIFFERENCES BETWEEN COSTS
|
| |
A
project affecting 1000 existing employees in Department
A involves a new project team of 10 additional people, plus
an informal ‘secondment’ from Department B of
another 15 people for six months each. Department B has
also agreed to fund half of the additional cashflows expected
to be incurred.
 |
The
additional cashflows involve the costs of
employing the additional 10 people. |
 |
The
economic cost of the proposal includes the
cashflows of the additional 10 people, the costs to
the 1000 employees affected in Department A (for instance,
reflecting the cost of their time), and the costs
of the 15 staff transferred. |
 |
A
brief funding statement could show that Department
B is providing half the additional cashflows expected
to be incurred. |
 |
Both
departments will need to consider how the transfers
affect their staff resource profiles, and potentially
other internal budgets. |
|
|
|
back
to top
DEVELOPING
THE SOLUTION
|
Introduction
|
6.12 |
The
best option is likely to require further refinement before a solution
emerges. Options are rarely completely mutually exclusive, so it
is useful to review the other options to see if their good parts
can be grafted onto the leading option.
|
Consultation
|
6.13 |
Consultation
with external experts and with those affected is very important
at this stage, whether or not formal or informal consultation has
taken place earlier on.
|
6.14 |
Consultation
on projects will usually be on one or two lead proposals; whereas
consultation on policy and programme proposals that have more widespread
effects should usually be undertaken both earlier, and on a wide
range of options and alternatives.
|
6.15 |
Analysis
of who is affected by a proposal, undertaken as part of the appraisal,
may be very useful in determining who should be consulted, and also
in considering the details of implementation. Attention should be
drawn to the key assumptions, options and implementation issues.
Consultation exercises should be drawn up in line with the following
best practice guidelines:3
|
| |
 |
Use
the most appropriate approach. Written consultation may not
the best way to canvass views on a policy or project option.
Methods include meetings with interested parties and user
surveys. |
 |
Consultation
should be easy to respond to (e.g., by electronic means). |
 |
Check
if statutory obligations apply. |
 |
Allow
sufficient time; consultation should be built into the planning
process at the start. |
 |
Be
clear about who is being consulted, about what, in what time-scale,
for what purpose. |
 |
Consider
joining up with other consultations, for instance in other
government departments. |
 |
Consultation
documents should be clear, concise and focused. |
 |
Ensure
that the process reaches the target audience. |
 |
Ensure
that people are told the results, and the reasons for decisions
taken. |
|
|
back
to top
Involving the private sector
|
6.16 |
The
extent of involvement of the private sector can vary from minor
elements of a proposal being contracted-out through to full privatisation,
with various forms of contracting, outsourcing and PPPs (including
PFI) in between. Public bodies need to consider carefully which
procurement route is likely to be most
effective. In some cases, the appropriate balance between public
or private sector provision will be clear. In others, the best solution
must be identified across a range of public, private and partnership
options. |
| |
BOX 23: CONSIDERING PRIVATE SECTOR PROVISION |
| |
Private sector provision may be more likely to provide
a better solution where the scope for the following
is greatest: |
|
Innovation
to reduce costs or to improve observable outcomes; |
|
Generating
additional revenue flows by sales to third parties; |
|
Reduction
in risk of cost overrun or benefit shortfall; |
|
A
contractor is able to exploit economies of scale in
the provision of services (e.g. IT support or facilities
maintenance); |
|
Savings
in whole life costs and/ or for improved outcomes through
effective design (e.g.: where a broad range of services
may be provided in association with an asset, or when
many inputs must be integrated in delivering a service,
or where whole life and operating costs are importantly
determined by good design); |
|
Clear
specification of quality standards in absolute terms
or in terms of client satisfaction; |
|
Ability
of private sector to control discrete elements of the
project without excessive oversight or interference;
or, |
|
Clear
boundaries and interfaces between public and private
sectors. |
Provision
by the private sector may be less appropriate where: |
|
Risks
which threaten the viability of a project are outside
the control of the contractor (and these risks cannot
be separated contractually from the project); |
|
The
predominant risks are ones where the public sector has
the comparative advantage in managing them; |
|
A
large degree of discretion is required in determining
the quality of services, and quality is not observable;
or, |
|
Bidding
costs are large in proportion to the value of the project
(although there may be means of reducing these costs).
|
|
|
|
Commercial
agreements
|
6.17 |
Appraisals
are generally made up of estimates that are forecast some time in
advance of either the projected costs being incurred or benefits
being realised. Any estimate made well in advance may or may not
prove to be correct once a project has been implemented. The less
well developed an appraisal, the greater the variability there is
likely to be between the estimated value attached to a cost or benefit
and the outturn.
|
6.18 |
By
transferring risk away from the public
sector in different ways, different procurement options provide
procuring authorities with choices about how they might manage and
mitigate certain risks around estimated
costs and benefits. For example, typically PFI contracts transfer
to the PFI partner the risk that capital costs will exceed estimates
made by the procuring authority in a way that some conventional
contracts may not. Equally, a payment mechanism that calibrates
payments made under a contract with the delivery of well-defined
benefits provides procuring authorities with a way of ensuring that
certain costs are incurred only if certain benefits are delivered.
|
6.19 |
The
level of confidence that public bodies can have that estimated costs
and benefits will be similar to eventual outturn will depend on:
|
| |
 |
The
length of time between the cost or benefit estimate being
made and the date of contract award; and |
 |
The
procurement option chosen. |
|
6.20 |
In relation to the latter, for example, costs which are fixed under
contract and which become payable against measured milestones of
physical progress in construction will have a higher probability
of being incurred than costs which, although fixed under contract,
are only payable to the extent that defined benefits, outcomes or
contractual outputs associated with the contract are delivered.
Comparisons between various procurement options
need to take account of the impact that different contractual terms
have on the likelihood that, in fact, certain costs will be incurred
and benefits realised at the level estimated by the procuring body. |
|
back
to top
Procurement processes
|
6.21 |
OGC
provides detailed guidance on the procurement options that are available,
and how to conduct the relevant procurement process.4
If the private sector is involved, proposals should be fully developed
before tenders are invited. Where implementation will be by procurement,
there are extensive requirements that need to be met under European
Commission Directives and also under regulations within the United
Kingdom.
|
6.22 |
Often,
these impose requirements over and above those stipulated by the
Green Book, and must be complied with at all stages. Specialist
advice can be sought from either the procurement unit within a department
or agency or from OGC5,
and from Partnerships UK6
for PPP and PFI projects. The OGC also provides
guidance on partnering arrangements.
|
IMPLEMENTATION
|
6.23 |
Implementation7
plans should be sufficiently complete to enable decisions to be
taken on whether or not to proceed. So that
evaluations can be completed satisfactorily later on, it is important
that during implementation, performance is tracked and measured,
and data captured for later analysis.
|
Programme
and project management
|
6.24 |
Economically
justifiable and financially affordable proposals are of no value
if realistically they cannot be implemented. The implementation
of proposals must be considered as part of the appraisal process,
enough to ensure at least that proposals are viable, risks are manageable,
and that benefits can be realised, before significant funds are
committed. These aspects of appraisal develop iteratively as with
the analysis of costs and benefits.
|
6.25 |
Programme
management is a structured framework for defining and implementing
change within an organisation. It provides a framework for implementing
business strategies and initiatives through the management of a
portfolio of projects that give organisations the capability to
achieve benefits that are of strategic importance. All large programmes
should have recognised programme management methodologies.
|
6.26 |
There
should be an agreed approach to the management of projects, using
recognised project management methodologies,
such as PRINCE2.8
Typically, this will involve identifying tasks and responsibilities
and deadlines for completing them, and producing baseline schedules
of milestones and activities (often in the form of Gantt charts).
Progress against the base schedule should be reported on a regular
basis. Guidance on project management is available from OGC.9
Specific guidance is available on the management of construction
projects.10
|
|
back
to top
Performance
management and measurement
|
6.27 |
Performance
management concerns tracking the success of a policy, programme
or project in achieving its objectives and in securing the expected
benefits. For appraisal and evaluation purposes, it involves the
systematic collection of data relating to the financial management
and outcomes of the policy, programme or project during implementation.
|
6.28 |
This
provides an essential source of information, indicating the extent
to which objectives are being achieved, giving an early warning
of potential problems, and of the possible need to adapt the policy,
programme or project to ensure success. Monitoring
also provides information for the evaluation stage. To be fully
effective, plans for monitoring must form part of the initial planning
of a policy, programme or project.
|
6.29 |
Effective
performance measurement and monitoring means tracking all
categories of benefit and ensuring that: |
|
Projects
have defined target benefits and outputs; |
|
Ownership
of the delivery of benefits remains with the programme manager; |
|
Outputs
of a project or policy remain consistent with changing government
objectives; |
|
Targets
and achieved benefits are measured, reported and communicated; |
|
Costs
are closely monitored and managed; and, |
|
Forecast
costs and benefits are frequently reviewed. |
|
6.30
|
A monitoring system should establish: |
| |
|
Whether
management data is actually measuring what it purports to
measure; and, |
|
Put
in place sufficient controls to ensure that the data is accurate. |
|
Financial reporting
|
6.31 |
Regular
financial reporting on policies, programmes and projects should
be performed. Reports may be integrated into
the normal financial reporting cycle of an organisation, issued
separately, or possibly combined with the reporting of progress
against plan, benefits, and risks.
|
6.32 |
Finance
reports are likely to show expenditure to date, forecasts for the
year, and variances against budgets. In large complex projects,
the financial reporting is likely to integrate with contract management,
with contractors providing regular ‘Work In Progress’
statements.
|
Benefits
realisation management
|
6.33 |
Benefits
realisation management is the identification of potential benefits,
their planning, modelling and tracking, the assignment of responsibilities
and authorities and their actual realisation. In many cases, benefits
realisation management should be carried out as a duty separate
from day to day project management.
|
6.34 |
Benefits
fall into four main categories, which are described below.
|
| |
BOX
24: BENEFIT CATEGORIES |
| |
Benefit |
|
Example |
|
Financial |
Quantitative |
Operating
cost reduction, revenue increase |
|
Non-financial |
Quantitative |
Number
of customer complaints, reduction in road accidents, percentage
of government departments on-line |
|
Non-financial |
Quantitative |
Staff
skills, staff morale |
|
Outcomes |
Quantitative
and qualitative |
Improved
standards of healthcare |
|
6.35
|
It is also useful to identify financial savings that release cash
for other uses.
|
|
back
to top
Contract
management
|
6.36 |
When
contracts have been let, it will be important to ensure that the
respective roles and responsibilities set out in the contract are
fully understood and fulfilled to the contracted standard. The likelihood
of the benefits being realised will be affected by the contractual
terms, and any incentives built in to the contract. Where contracted
standards are not fulfilled, the contracting public body should
apply mechanisms established in the contract to rectify any under-performance.
Guidance is available from OGC on dispute resolution.11 |
| |
 |
| 1 |
A
pay back period is the number of years before a project breaks
even; when total (discounted or undiscounted) benefits (net
of on-going costs) equal capital costs. This technique ignores
all benefits and costs arising after the break-even date and
is likely to distort project choice.
|
| 2 |
The
internal rate of return (IRR) is
the discount rate that would give a proposal a present value
of zero. IRR can be used to rank proposals. In the private
sector, hurdle IRRs are often used to test whether a proposal
should go ahead. The riskier the project is, the higher the
hurdle IRR. |
| 3 |
|
| 4 |
|
| 5 |
|
| 6 |
|
| 7 |
In
this context, ‘implementation’ refers to those
activities that are required during the period after appraisal
to put in place a policy, or complete a programme or project. |
| 8 |
|
| 9 |
|
| 10 |
OGC
and HM Treasury have produced a series of ten procurement
guides for construction projects. These are fully endorsed
by the National Audit Office. http://www.property.gov.uk/ |
| 11 |
|
|